Plumbing Permit Application and Inspection Tracker
Plumbing Permit Application and Inspection Tracker
Tracks plumbing permit application details and jurisdictional inspection milestones, including AHJ, permit number, rough-in, water test, gas test, and final inspection closeout.
Permit and AHJ Details
-
Authority Having Jurisdiction (AHJ)
Enter the jurisdiction or agency responsible for plan review and inspections.
-
Permit number
Record the issued plumbing permit number exactly as shown on the permit card or application.
-
Permit application status
Select the current permit status.
-
Project address
Enter the site address covered by the plumbing permit.
-
Permit issue date
Record the date and time the permit was issued, if available.
-
Plan review or permit notes
Capture jurisdiction-specific notes, conditions, or comments tied to the permit application.
Pre-Inspection Readiness
-
Approved plans or permit documents available on site
Approved drawings, permit card, or inspection paperwork is available for the inspector.
-
Work area accessible for inspection
Piping, fixtures, and test points are accessible without obstruction.
-
Required test equipment available and calibrated
Pressure gauges, test plugs, or other required equipment are present and within calibration or verification date.
-
Safety controls in place for inspection
PPE, access control, and site safety conditions are adequate for the inspection activity.
Rough-In Inspection
-
Rough-in inspection requested
Confirm that the rough-in inspection has been scheduled or requested with the AHJ.
-
Rough-in inspection date
Record the date and time of the rough-in inspection.
-
Concealed piping installed per approved plans
Installed piping, fittings, and routing match the approved permit documents and scope.
-
Pipe supports, protection, and clearances acceptable
Supports, hangers, protection from damage, and required clearances are acceptable for rough-in.
-
Rough-in deficiencies noted
List any deficiencies, non-conformances, or correction items identified during rough-in inspection.
Water Test Inspection
-
Water test required by AHJ
Confirm whether the jurisdiction requires a water test for this plumbing scope.
-
Water test date
Record the date and time the water test was performed.
-
Test pressure
Enter the water test pressure used during the inspection.
-
Test duration
Enter the duration of the water test.
-
Water test passed without leakage
No visible leakage, pressure loss, or other failure was observed during the test period.
Gas Test Inspection
-
Gas test required for scope
Confirm whether gas piping is included and a gas test is required for this permit.
-
Gas test date
Record the date and time of the gas test.
-
Gas test pressure
Enter the pressure used for the gas test.
-
Gas test passed without leakage
No leakage, pressure drop, or unsafe condition was observed during the gas test.
Final Inspection and Closeout
-
Final inspection requested
Confirm that the final inspection has been requested with the AHJ.
-
Final inspection date
Record the date and time of the final inspection.
-
Final inspection result
Select the outcome of the final inspection.
-
Final deficiencies and correction items
Document any deficiencies, non-conformances, or correction items identified at final inspection.
-
Permit closed out
Confirm that the permit has been closed or final approval has been recorded by the AHJ.