Partial Discharge Test - Solid Dielectric Module
Partial Discharge Test - Solid Dielectric Module
Inspection template for recording partial discharge measurements on epoxy-encapsulated and solid dielectric switchgear components to identify voids, insulation defects, and manufacturing anomalies during routine testing of cast modules.
Test Identification and Scope
-
Module identification recorded
Record the module serial number, part number, voltage class, and test station identifier.
-
Test type confirmed as routine partial discharge test
Confirm this is a 100 percent routine test on a cast solid dielectric or epoxy-encapsulated module.
-
Test standard or procedure referenced
Enter the applicable internal procedure, customer specification, or test method reference used for this inspection.
Safety Preconditions and Test Setup
-
Lockout-tagout applied where required
Verify the test article and associated circuits are de-energized and controlled per site lockout-tagout procedure.
-
Work area controlled and access restricted
Confirm barriers, signage, and access control are in place to keep unauthorized personnel clear of the test area.
-
Required PPE worn
Select all PPE used for the test setup and measurement activity.
-
Test equipment calibration current
Confirm the partial discharge detector, sensors, and any coupling or measurement accessories are within calibration date.
Environmental and Instrument Conditions
-
Ambient temperature
Record ambient temperature at the test location.
-
Relative humidity
Record relative humidity at the test location.
-
Background noise or interference acceptable
Confirm the electromagnetic or acoustic background level does not prevent reliable partial discharge measurement.
-
Measurement method selected
Select the partial discharge detection method used for this test.
Partial Discharge Measurements
-
Test voltage applied
Record the applied test voltage during the measurement.
-
Measured partial discharge level
Record the measured partial discharge magnitude at the specified test point.
-
Measurement location or test point
Identify the module, phase, bushing, termination, or other location where the reading was taken.
-
Repeat reading stable
Confirm the reading is repeatable and not caused by transient interference or setup instability.
Defects, Findings, and Disposition
-
Evidence of voids, cracks, or insulation defects observed
Record whether the test or visual review identified signs of voids, cracks, delamination, tracking, or other insulation anomalies.
-
Corrective action or disposition recorded
Document the disposition for any non-conformance, including re-test, repair, hold, or reject status.
-
Photo evidence captured
Attach photos of the test setup, instrument display, or any defect indication as applicable.
Final Review and Sign-Off
-
Inspection result accepted
Confirm the module meets the acceptance criteria for the routine partial discharge test.
-
Inspector signature
Inspector or competent person sign-off confirming the record is complete and accurate.
-
Review date and time
Record when the inspection record was completed and reviewed.