Module Setting and Placement Record
Module Setting and Placement Record
Inspection record for documenting prefabricated module setting, including survey verification, leveling, anchorage and connection checks, tolerance confirmation, and close-out signoff for industrial installations.
Inspection Details and Scope
-
Project, module, and location identified
Record the project name, module ID, set location, and work area.
-
Inspection date and time recorded
Document when the module setting and placement inspection was performed.
-
Responsible contractor and inspector identified
Identify the installing contractor, competent person, and inspector.
- Applicable drawings, lift plan, and installation procedure available
Pre-Set Site and Foundation Readiness
-
Foundation, supports, or bearing surfaces verified ready for set
Confirm the receiving surface is complete, clean, and capable of supporting the module.
-
Survey control points and benchmarks verified
Confirm control points, benchmarks, and reference elevations are established and protected.
-
Obstructions, debris, and trip hazards cleared from set area
Verify the module landing area is clear and safe for placement.
-
Weather and site conditions acceptable for placement
Document wind, precipitation, visibility, and ground conditions affecting safe placement.
Survey, Elevation, and Level Verification
-
Module elevation matches design target
Record measured elevation variance from design or benchmark.
-
Module level verified along primary axis
Record out-of-level condition along the primary axis.
-
Module level verified along secondary axis
Record out-of-level condition along the secondary axis.
-
Plumb, alignment, and orientation within tolerance
Verify module is plumb, aligned to grid, and oriented correctly relative to the set-out lines.
Connections, Anchorage, and Interface Checks
-
Anchorage or tie-down connections installed and secured
Confirm all required anchors, bolts, welds, or tie-downs are installed per specification.
-
Mechanical, structural, and utility interfaces connected correctly
Verify interface connections are complete and properly engaged.
-
Connection torque or fastening verification recorded
Record measured torque or fastening value where applicable.
-
Temporary supports, rigging, and lifting gear removed or released
Confirm the module is stable and no temporary lifting equipment remains attached.
Tolerance, Quality, and Safety Verification
-
Specified dimensional tolerances met
Confirm the installed module meets project tolerance requirements for position, elevation, and alignment.
-
Visible damage, distortion, or coating defects observed
Document any damage, deformation, or finish defects noted after placement.
-
Work area controlled and safe for next trade
Verify housekeeping, barricades, and access control are appropriate before turnover.
Deficiencies, Corrective Actions, and Sign-Off
-
Deficiencies or non-conformances documented
Select all deficiencies identified during inspection.
-
Corrective actions assigned
Describe corrective actions, responsible party, and target completion date.
-
Inspector signature
Inspector attestation that the record is complete and accurate.
-
Supervisor or owner representative approval
Approval sign-off for acceptance or conditional acceptance of the module set.
Ask AI
Template Studio