Medical Gas Piping Verification Inspection - NFPA 99

Medical Gas Piping Verification Inspection - NFPA 99

Verification testing record for medical gas piping systems per NFPA 99, documenting pressure test results, cross-connection verification, particulate cleanliness, final tie-in readiness, and ASSE 6030 verifier sign-off.

Inspection Identification

  • Project, facility, and system identification recorded
    Document the project name, facility name, building/wing, system identifier, and service type being verified.
  • Inspection date and time recorded
    Record the date and time the verification inspection was performed.
  • Verifier identified as ASSE 6030 qualified
    Confirm the inspector/verifier is qualified to perform medical gas verification testing as required by the project and NFPA 99 workflow.

Pre-Test Conditions and Safety

  • Permits, shutdown approvals, and AHJ requirements confirmed
    Verify required permits, shutdown notifications, and Authority Having Jurisdiction requirements are in place before testing.
  • Piping section isolated and identified for test
    Confirm the test boundary is isolated, tagged, and clearly identified to prevent unintended service interruption or cross-connection.
  • Test equipment calibrated and within certification date
    Verify gauges, pressure devices, and any particulate test equipment are calibrated and traceable to current certification.
  • System components installed and ready for verification
    Select the components that are installed and included in the verification scope.

Pressure Test Verification

  • Test medium matches approved procedure
    Confirm the test medium used for pressure testing matches the approved procedure and project requirements.
  • Test pressure recorded
    Record the applied test pressure used for the verification test.
  • Pressure hold duration recorded
    Record the duration the system held test pressure during observation.
  • No pressure loss or visible leakage observed
    Confirm the piping section maintained pressure with no visible leakage, deformation, or other deficiency during the hold period.

Cross-Connection and Label Verification

  • Cross-connection test completed
    Confirm the cross-connection test was performed on the medical gas piping system.
  • No cross-connections detected between gas services
    Verify that outlets, piping, valves, and source connections are correctly connected to the intended gas service and no cross-connection exists.
  • System labeling and identification are correct
    Confirm piping, outlets, valves, and source components are labeled with the correct gas designation and directional identification where required.
  • Terminal units and source points match documented gas service
    Verify terminal units, manifold connections, and source points correspond to the documented medical gas service and installation drawings.

Particulate Cleanliness and Final Tie-In

  • Particulate test completed
    Confirm particulate cleanliness testing was completed for the piping section as required by the project specification and verification procedure.
  • Particulate test result acceptable
    Verify the particulate test result met the acceptance criteria for the medical gas piping system.
  • Final tie-in approved for service
    Confirm the system is approved for final tie-in only after successful verification testing and required corrections are complete.

Deficiencies and Sign-Off

  • Deficiencies or non-conformances documented
    Record all deficiencies, non-conformances, corrective actions, and retest requirements.
  • Inspector signature
    Signature of the qualified verifier completing the inspection.
Ask AI Template Studio

Let's customize Medical Gas Piping Verification Inspection - NFPA 99.

Tell me how you'd like to adapt it. For example:

  • Add a question about delivery time.
  • Make it shorter — 5 questions max.
  • Tailor it for the hospitality industry.
  • Translate the labels into Spanish.