Critical Lift Plan Documentation

Critical Lift Plan Documentation

Engineered critical lift plan inspection for non-routine crane and rigging lifts, capturing load weight, crane configuration, lift radii, ground bearing conditions, and signal protocols before execution.

Lift Plan Authorization

  • Lift plan completed and approved before mobilization
    Documented lift plan is present, current, and approved by the responsible competent person or designated authority before crane setup begins.
  • Lift classified as critical or non-routine
    Lift meets site criteria for a critical lift, engineered lift, tandem lift, personnel-adjacent lift, or other non-routine operation requiring enhanced controls.
  • Pre-lift briefing completed with crew
    Lift briefing reviewed the sequence, roles, hazards, exclusion zone, stop-work authority, and emergency actions with all involved personnel.
  • Competent person and signal person identified
    A competent person and qualified signal person are assigned and understood by the crew.
  • Required permits, engineering review, and site approvals present
    Any required permits, engineered calculations, customer approvals, and site authorization documents are available at the jobsite.

Load and Rigging Verification

  • Verified load weight recorded
    Actual or calculated load weight is documented, including all rigging, hooks, spreaders, and attachments to be lifted.
  • Load center of gravity identified
    Center of gravity is identified and accounted for in the lift plan and rigging arrangement.
  • Rigging gear selected for load and configuration
    Slings, shackles, hooks, spreaders, and other rigging hardware are rated for the load and compatible with the lift geometry.
  • Rigging inspection completed
    All rigging components were inspected before use and show no visible damage, deformation, excessive wear, or missing identification.
  • Attachment points verified
    Load attachment points, lifting lugs, and connection hardware are verified as suitable for the planned lift path and forces.

Crane Configuration and Capacity

  • Crane make, model, and configuration documented
    Crane type, make/model, boom length, counterweight, jib, and outrigger configuration are recorded in the lift plan.
  • Planned load radius verified
    Planned working radius is measured and matches the crane chart configuration used for capacity calculations.
  • Crane capacity adequate at planned radius
    Planned load, including rigging and dynamic factors, remains within the crane's rated capacity for the selected configuration and radius.
  • Load percentage of rated capacity documented
    Calculated load percentage at the planned radius is documented and reviewed for critical lift criteria.
  • Anti-two-block, load moment, and safety devices functional
    Required crane safety devices are present and functional for the planned operation.

Ground Bearing and Site Conditions

  • Ground bearing capacity verified
    Ground or support surface capacity has been reviewed and is adequate for crane loading, outrigger reactions, and lift path conditions.
  • Outrigger mats or cribbing installed as planned
    Mats, pads, or cribbing are installed per the lift plan and sized for the expected load distribution.
  • Setup area level within plan tolerance
    Crane setup area is level within the tolerance specified by the manufacturer or lift plan.
  • Overhead and side obstructions cleared
    Power lines, structures, plant equipment, and other obstructions are identified and controlled for the planned boom path and load path.
  • Weather conditions within lift limits
    Wind, visibility, precipitation, and lightning conditions are within the limits established by the lift plan and manufacturer guidance.

Communication, Exclusion Zone, and Final Sign-Off

  • Primary signal protocol established
    Primary communication method is defined, including hand signals, radio channel, or designated signal person authority.
  • Exclusion zone established and controlled
    Barricades, spotters, or other controls prevent unauthorized personnel from entering the lift area.
  • Tag lines and load control methods available
    Tag lines or other approved load control methods are available where needed to control rotation and swing.
  • Stop-work authority communicated
    Crew understands that any worker may stop the lift if conditions change or a hazard is identified.
  • Final authorization to proceed
    Responsible supervisor or competent person authorizes the lift after all critical items are verified.
Ask AI Template Studio

Let's customize Critical Lift Plan Documentation.

Tell me how you'd like to adapt it. For example:

  • Add a question about delivery time.
  • Make it shorter — 5 questions max.
  • Tailor it for the hospitality industry.
  • Translate the labels into Spanish.