Critical Lift Plan Documentation
Critical Lift Plan Documentation
Engineered critical lift plan inspection for non-routine crane and rigging lifts, capturing load weight, crane configuration, lift radii, ground bearing conditions, and signal protocols before execution.
Lift Plan Authorization
-
Lift plan completed and approved before mobilization
Documented lift plan is present, current, and approved by the responsible competent person or designated authority before crane setup begins.
-
Lift classified as critical or non-routine
Lift meets site criteria for a critical lift, engineered lift, tandem lift, personnel-adjacent lift, or other non-routine operation requiring enhanced controls.
-
Pre-lift briefing completed with crew
Lift briefing reviewed the sequence, roles, hazards, exclusion zone, stop-work authority, and emergency actions with all involved personnel.
-
Competent person and signal person identified
A competent person and qualified signal person are assigned and understood by the crew.
-
Required permits, engineering review, and site approvals present
Any required permits, engineered calculations, customer approvals, and site authorization documents are available at the jobsite.
Load and Rigging Verification
-
Verified load weight recorded
Actual or calculated load weight is documented, including all rigging, hooks, spreaders, and attachments to be lifted.
-
Load center of gravity identified
Center of gravity is identified and accounted for in the lift plan and rigging arrangement.
-
Rigging gear selected for load and configuration
Slings, shackles, hooks, spreaders, and other rigging hardware are rated for the load and compatible with the lift geometry.
-
Rigging inspection completed
All rigging components were inspected before use and show no visible damage, deformation, excessive wear, or missing identification.
-
Attachment points verified
Load attachment points, lifting lugs, and connection hardware are verified as suitable for the planned lift path and forces.
Crane Configuration and Capacity
-
Crane make, model, and configuration documented
Crane type, make/model, boom length, counterweight, jib, and outrigger configuration are recorded in the lift plan.
-
Planned load radius verified
Planned working radius is measured and matches the crane chart configuration used for capacity calculations.
-
Crane capacity adequate at planned radius
Planned load, including rigging and dynamic factors, remains within the crane's rated capacity for the selected configuration and radius.
-
Load percentage of rated capacity documented
Calculated load percentage at the planned radius is documented and reviewed for critical lift criteria.
-
Anti-two-block, load moment, and safety devices functional
Required crane safety devices are present and functional for the planned operation.
Ground Bearing and Site Conditions
-
Ground bearing capacity verified
Ground or support surface capacity has been reviewed and is adequate for crane loading, outrigger reactions, and lift path conditions.
-
Outrigger mats or cribbing installed as planned
Mats, pads, or cribbing are installed per the lift plan and sized for the expected load distribution.
-
Setup area level within plan tolerance
Crane setup area is level within the tolerance specified by the manufacturer or lift plan.
-
Overhead and side obstructions cleared
Power lines, structures, plant equipment, and other obstructions are identified and controlled for the planned boom path and load path.
-
Weather conditions within lift limits
Wind, visibility, precipitation, and lightning conditions are within the limits established by the lift plan and manufacturer guidance.
Communication, Exclusion Zone, and Final Sign-Off
-
Primary signal protocol established
Primary communication method is defined, including hand signals, radio channel, or designated signal person authority.
-
Exclusion zone established and controlled
Barricades, spotters, or other controls prevent unauthorized personnel from entering the lift area.
-
Tag lines and load control methods available
Tag lines or other approved load control methods are available where needed to control rotation and swing.
-
Stop-work authority communicated
Crew understands that any worker may stop the lift if conditions change or a hazard is identified.
-
Final authorization to proceed
Responsible supervisor or competent person authorizes the lift after all critical items are verified.