Inspection Scope and Boiler Identification
-
Boiler identification recorded
Record boiler tag number, manufacturer, model, serial number, capacity, and location.
-
Inspection date and inspector credentials recorded
Document the inspection date, inspector name, and license or authorization details as required by the AHJ.
-
Boiler type and service verified
Confirm the boiler type and service category for the record.
-
Inspection scope includes external and internal examination
Verify that both external and internal inspection activities are included in this annual review.
-
Applicable jurisdiction and code basis documented
Record the state jurisdiction, ASME Section VI reference, and any applicable local boiler rules used for the inspection.
Certificate Posting and Compliance Records
-
Current boiler inspection certificate posted or available
Confirm the current annual inspection certificate is posted at the boiler or maintained where required by the AHJ.
-
Certificate matches boiler identification
Verify the certificate or record matches the boiler location, serial number, and jurisdiction.
-
Certificate issue and expiration dates recorded
Record the issue date, expiration date, and inspection cycle applicable to this boiler.
-
Prior deficiencies and corrective actions reviewed
Confirm previous inspection findings were reviewed and closed or tracked to completion.
-
Required records available for AHJ review
Verify maintenance logs, repair records, and prior inspection reports are available for review.
External Condition and Operating Controls
-
No active leaks, visible corrosion, or abnormal staining
Inspect the boiler exterior, piping, fittings, and nearby surfaces for leaks, corrosion, or evidence of water discharge.
-
Pressure/temperature gauges readable and within normal operating range
Verify gauges are legible, properly mounted, and indicate normal operating conditions.
-
Low-water cutoff, pressure controls, and operating controls present and intact
Confirm required operating and safety controls are installed, accessible, and show no visible damage.
-
Safety relief valve discharge piping and termination acceptable
Verify discharge piping is properly routed, unobstructed, and terminates in a safe location.
-
Burner, ignition, and fuel train area free of obvious defects
Check for damaged components, loose connections, soot accumulation, or signs of improper combustion.
-
Housekeeping and access around boiler adequate
Verify the boiler room is accessible, free of combustible storage in unsafe proximity, and allows safe inspection and maintenance access.
Internal Condition and Water-Side Examination
-
Boiler safely shut down, isolated, and opened for internal inspection
Confirm lockout-tagout, isolation, depressurization, and safe access were completed before internal examination.
-
Internal surfaces free of heavy scale, sludge, or pitting
Inspect waterside surfaces for scale buildup, sludge, pitting, or other deterioration affecting safe operation.
-
No evidence of cracking, bulging, distortion, or overheating
Check pressure parts, tubes, drums, and accessible internal surfaces for structural distress or heat damage.
-
Water-side corrosion condition documented
Rate the overall internal corrosion condition observed during inspection.
-
Manway, handhole, and gasket surfaces acceptable
Verify openings, covers, and gasket surfaces are serviceable and free of damage that would prevent proper reassembly.
-
Internal inspection findings documented
Record all internal observations, including deposits, repairs needed, and any areas requiring follow-up.
Safety Devices, Testing, and Corrective Actions
-
Safety relief valve condition acceptable
Confirm the relief valve shows no leakage, corrosion, tampering, or signs of improper installation.
-
Required safety device tests performed or witnessed
Record whether applicable safety device tests were performed, witnessed, or verified per site procedure and jurisdictional requirements.
-
Deficiencies and non-conformances documented
List all deficiencies, non-conformances, and critical items requiring repair, retest, or AHJ notification.
-
Corrective action owner and due date assigned
Identify the responsible person or contractor and the target completion date for each corrective action.