Run: Weld Visual Inspection Log (AWS D1.1)

Use this Weld Visual Inspection Log to record AWS D1.1 visual checks, trace welds to the WPS and welder, and document acceptance or repair disposition in one...

Fill this out, get a PDF emailed to you. No account required. Want to run it with your team and track results? Sign up free →

Inspection Identification and Traceability

Record the project name, work order, drawing number, or fabrication package being inspected.
Capture the date and time the visual inspection was performed.
Record inspector name and qualification status. For AWS D1.1 visual inspection, document the certified welding inspector (CWI) or other authorized inspector per project requirements.
Record shop, field, bay, station, or structure location where the weld was inspected.
Select when the inspection occurred in the weld lifecycle.

Weld and Joint Traceability

Record joint number, weld ID, location, or other unique identifier tied to the weld.
Record member size, material designation, thickness, and configuration as needed for traceability.
Select the weld type being inspected.
Record the welder identification number or stamp associated with the weld.
Record the welding procedure specification (WPS) number or revision used for the weld.

Visual Inspection Conditions and Method

Confirm the weld area is sufficiently clean and accessible for visual inspection.
Record measured lighting at the inspection point. Use project or site criteria if more stringent.
Confirm the inspector could view the weld, toes, root area, and adjacent base metal as required.
Confirm required gauges, fillet weld gauges, rulers, or other measuring tools were available and within calibration status if applicable.

Visual Weld Acceptance Criteria

Record whether any crack is present in the weld metal, HAZ, or adjacent base metal.
Confirm undercut does not exceed project or AWS D1.1 acceptance criteria.
Record whether overlap or cold lap is present.
Confirm visible porosity, worm tracks, slag, or other surface discontinuities meet acceptance criteria.
Confirm weld size, leg length, reinforcement, contour, and profile are acceptable for the joint and WPS.
Record any visible arc strikes, excessive spatter, or gouges that require evaluation or repair.

Defects, Disposition, and Sign-Off

Describe all observed defects or non-conformances, including location, size, and extent where applicable.
Record the final inspection disposition for the weld.
Record NCR number, repair ticket, or corrective action reference if the weld did not pass.
Inspector sign-off confirming the inspection record is complete and accurate.

Get your results

Enter your email — we'll send you a PDF of your filled-out template, plus the occasional MangoScoop newsletter (templates, workflow tips, product updates). Unsubscribe anytime — link is in every email.

Generated with MangoApps Templates — browse 250+ free
Ask AI Product Advisor

Hi! I'm the MangoApps Product Advisor. I can help you with:

  • Understanding our 40+ workplace apps
  • Finding the right solution for your needs
  • Answering questions about pricing and features
  • Pointing you to free tools you can try right now

What would you like to know?