Run: Transformer Turns Ratio (TTR) Test Inspection

Record transformer turns ratio measurements at every tap position and compare them to the design ratio. Use this template to catch winding, polarity, and tap...

Fill this out, get a PDF emailed to you. No account required. Want to run it with your team and track results? Sign up free →

Test Setup and Equipment Identification

Verify transformer serial number, asset ID, voltage class, and phase designation against the work order and nameplate.
Confirm the TTR test set is within calibration and appropriate for the transformer voltage class and winding configuration.
Confirm the transformer is de-energized, grounded as required, and controlled under lockout-tagout before testing.
Record ambient temperature, humidity if required by procedure, and any conditions that could affect test interpretation.
Enter the procedure, standard work instruction, or commissioning checklist used for this inspection.

Design Ratio and Tap Configuration

Record the expected design ratio for each applicable winding pair before testing.
Identify whether the transformer uses de-energized tap changing or on-load tap changing and record the available tap range.
Confirm the full tap sequence to be tested, including neutral and all raise/lower positions as applicable.
Enter the allowable deviation from design ratio per manufacturer specification or site acceptance criteria.

Turns Ratio Measurements by Tap Position

Record the measured ratio at the neutral tap and compare it to the design ratio.
Record the measured ratio for each raise tap position tested and note any deviation from the design ratio.
Record the measured ratio for each lower tap position tested and note any deviation from the design ratio.
Document the percent deviation between measured and design ratio for each tap position.
Confirm that every tested tap position is within the specified tolerance band.

Winding and Tap Changer Integrity

Assess test results for signs of winding defects, incorrect connections, or polarity issues.
Verify the tap changer moved and indexed correctly through the full range without binding, misalignment, or abnormal behavior.
Record any abnormal condition observed during setup, tap changes, or measurement.
List any deficiencies, non-conformances, or follow-up actions required before energization.

Results, Corrective Action, and Sign-off

Select the overall outcome of the TTR inspection.
Describe any corrective action, retest requirement, or escalation to engineering or the AHJ if applicable.
Inspector sign-off confirming the recorded measurements and findings are accurate.

Get your results

Enter your email — we'll send you a PDF of your filled-out template, plus the occasional MangoScoop newsletter (templates, workflow tips, product updates). Unsubscribe anytime — link is in every email.

Generated with MangoApps Templates — browse 250+ free
Ask AI Product Advisor

Hi! I'm the MangoApps Product Advisor. I can help you with:

  • Understanding our 40+ workplace apps
  • Finding the right solution for your needs
  • Answering questions about pricing and features
  • Pointing you to free tools you can try right now

What would you like to know?