Run: HDD Pre-Bore Daily Safety Walkdown

Pre-bore safety walkdown for horizontal directional drilling crews to verify the bore plan, utility locates, exclusion zones, tracker communication, and go/n...

Fill this out, get a PDF emailed to you. No account required. Want to run it with your team and track results? Sign up free →

Inspection Setup

Record the project name or location, inspection date, and crew or foreman name.
Confirm the person completing the walkdown is authorized to stop work and correct hazards.
Verify the inspection is performed before any bore initiation or reaming activity.
Confirm weather, visibility, access, and ground conditions do not create an immediate hazard for the planned work.

Bore Plan and Work Scope Review

Confirm the latest approved bore plan, drawings, or work package is present at the jobsite.
Verify the planned entry and exit locations are marked and match the current bore plan.
Confirm the crew reviewed the intended bore depth, alignment, and any known changes to the route.
Verify any changes in site conditions, nearby work, traffic, or surface hazards were communicated before work starts.

Utility Locate Verification

Verify all required utility markings are present, legible, and visible in the bore area.
Confirm the locate marks were checked against the planned bore path and offsets before drilling.
Verify test holes, potholing, or daylighting were completed at required crossings or conflict points.
Confirm any unmarked, conflicting, or uncertain utility information was reported and resolved before drilling begins.

Exclusion Zone and Site Controls

Verify the exclusion zone is set up around the drill, bore path, and support equipment as required by the job plan.
Confirm physical controls are positioned to keep unauthorized personnel out of the work area.
Verify spotters, flagging, detours, or other controls are in place if the work affects traffic or pedestrian movement.
Confirm the work area maintains required clearance from overhead lines, structures, and underground conflict points.

Tracker Communication and Equipment Readiness

Confirm the locator/tracker and drill operator can communicate clearly using the agreed method before drilling starts.
Verify the tracking system is powered on, operating normally, and set up for the planned bore.
Confirm the crew reviewed stop-work signals, emergency shutdown steps, and escalation contacts.

PPE and Final Go/No-Go

Verify the crew is wearing job-required PPE such as hard hats, hi-vis apparel, eye protection, gloves, and protective footwear.
Confirm all critical items are complete and no unresolved deficiency remains that would prevent a safe start.