Run: Ground Resistance Fall-of-Potential Test Record

Record three-point fall-of-potential ground resistance tests with setup, soil conditions, readings, and pass/fail notes in one place. Use it to document IEEE...

Fill this out, get a PDF emailed to you. No account required. Want to run it with your team and track results? Sign up free →

Inspection Details

Record facility name, building/area, grounding electrode system identifier, and test point location.
Confirm the tester is a competent person or otherwise authorized by site procedure.

Safety and Test Preconditions

Verify access control, trip hazards, traffic exposure, and any energized equipment hazards near the test route.
Select all PPE used for the task.
Confirm the grounding electrode system and connected equipment are isolated per site procedure before testing.
Record ambient temperature, precipitation, recent rainfall, and soil condition because they can affect readings.

Test Equipment and Setup

Record meter make, model, serial number, and calibration due date.
Verify leads are intact, properly connected, and long enough for the planned probe spacing.
Confirm bonding jumpers, neutral connections, and parallel grounding paths were disconnected as required for a valid fall-of-potential test.
Enter the distance from the ground electrode to the current probe and potential probe positions.

Soil Resistivity and Site Conditions

Enter the measured soil resistivity used to interpret the ground resistance result, if available.
Select the observed soil condition at the time of test.
Document whether excavation, backfill, paving, or utility work may have affected the grounding system or soil conditions.

Test Results and Acceptance

Enter the final ground resistance value obtained from the three-point fall-of-potential test.
Confirm the measured resistance meets the applicable acceptance criterion used by the facility.
Confirm readings were taken at more than one probe position to verify a stable fall-of-potential curve.
Record any unstable readings, interference, nearby buried metal, or other factors affecting test validity.

Deficiencies, Corrective Actions, and Sign-Off

Indicate whether any non-conformance, defect, or abnormal condition was observed during the inspection.
Describe corrective actions, retest requirements, or escalation to the AHJ or responsible electrical authority.

Get your results

Enter your email — we'll send you a PDF of your filled-out template, plus the occasional MangoScoop newsletter (templates, workflow tips, product updates). Unsubscribe anytime — link is in every email.

Generated with MangoApps Templates — browse 250+ free
Ask AI Product Advisor

Hi! I'm the MangoApps Product Advisor. I can help you with:

  • Understanding our 40+ workplace apps
  • Finding the right solution for your needs
  • Answering questions about pricing and features
  • Pointing you to free tools you can try right now

What would you like to know?