Inspection Setup and Traceability
-
Inspection package includes current drawing, specification, PO, and revision-controlled work instructions
Verify the inspection package is complete and matches the current released configuration.
-
Part number and revision match the traveler and drawing
Confirm the part number, dash number, and revision status are consistent across all records.
-
Serial number or lot/batch identification recorded
Record the unique identifier used to trace the inspected part or lot.
-
Inspection equipment calibrated and within due date
Verify all measurement tools used for the inspection are in calibration and suitable for the tolerance range.
-
Environmental conditions suitable for measurement
Confirm temperature, lighting, and cleanliness are adequate to support accurate inspection results.
-
Inspection status of part
Select the disposition of the part being inspected.
AS9102 Form 1 - Part Number Accountability
-
Part number recorded exactly as released
Enter the released part number exactly as shown on the controlled drawing or purchase order.
-
Part name / nomenclature recorded
Record the formal part name or nomenclature associated with the drawing.
-
Part revision level recorded
Capture the current revision level for the part and drawing.
-
Reason for first article inspection identified
Select the reason the first article inspection is being performed.
-
Manufacturing source and location recorded
Record the manufacturing site, work center, or supplier source used to produce the part.
-
Customer purchase order or contract number recorded
Capture the customer PO, contract, or release number associated with the first article.
AS9102 Form 2 - Product Accountability
-
Raw material certification matches drawing specification
Verify the material certification matches the specified alloy, grade, temper, form, and applicable specification.
-
Material heat/lot number traceable to received certification
Confirm the heat, lot, or batch number on the part traces to the certification package.
-
Special process certifications reviewed
Select all special processes applicable to the part and verify supporting certifications are present.
-
Certificate of Conformance present for purchased or processed items
Confirm certificates of conformance are available for all applicable purchased or outsourced items.
-
Functional test or product verification evidence reviewed
Verify any required functional, fit, or product-level test evidence is complete and acceptable.
-
Nonconforming material or concessions identified
Identify any open nonconformance, deviation, waiver, or concession affecting the first article.
Dimensional Verification
-
All drawing dimensions measured and recorded
Confirm every applicable dimension, note, and characteristic on the drawing has been measured or otherwise accounted for.
-
Critical-to-quality characteristics within tolerance
Verify all critical or key characteristics meet the specified tolerance limits.
-
Measured dimensions recorded with units
Enter measured values and units for the inspected characteristic or attach the detailed measurement report.
-
Tolerance limits recorded
Record the nominal dimension and tolerance limits used to evaluate the measured result.
-
Measurement method identified
Select the primary method used to verify the characteristic.
-
Out-of-tolerance characteristics documented
Document any characteristic that is out of tolerance and reference the associated nonconformance record.
AS9102 Form 3 - Characteristic Accountability
-
Each drawing characteristic assigned a unique characteristic number
Confirm each requirement is uniquely numbered or otherwise cross-referenced for traceability.
-
Characteristic description matches drawing requirement
Verify the characteristic description matches the drawing note, dimension, or specification requirement.
-
Inspection result recorded for each characteristic
Confirm pass/fail or measured result is recorded for every characteristic.
-
Evidence of inspection method or report attached
Attach or reference the inspection report, CMM output, or other supporting evidence.
Final Review and Approval
-
All required AS9102 forms complete
Confirm Forms 1, 2, and 3 are complete and internally consistent.
-
Open nonconformances or corrective actions documented
Record any open issues requiring containment, corrective action, or customer disposition.
-
Inspector signature
Inspector signs to confirm the first article inspection was completed accurately.
-
Quality approval signature
Quality representative approves the completed first article package.