First article inspection template for AS9102 compliance, covering Form 1, Form 2, Form 3, dimensional verification, and material certification review.

Inspection Setup and Traceability

  • Inspection package includes current drawing, specification, PO, and revision-controlled work instructions
    Verify the inspection package is complete and matches the current released configuration.
  • Part number and revision match the traveler and drawing
    Confirm the part number, dash number, and revision status are consistent across all records.
  • Serial number or lot/batch identification recorded
    Record the unique identifier used to trace the inspected part or lot.
  • Inspection equipment calibrated and within due date
    Verify all measurement tools used for the inspection are in calibration and suitable for the tolerance range.
  • Environmental conditions suitable for measurement
    Confirm temperature, lighting, and cleanliness are adequate to support accurate inspection results.
  • Inspection status of part
    Select the disposition of the part being inspected.

AS9102 Form 1 - Part Number Accountability

  • Part number recorded exactly as released
    Enter the released part number exactly as shown on the controlled drawing or purchase order.
  • Part name / nomenclature recorded
    Record the formal part name or nomenclature associated with the drawing.
  • Part revision level recorded
    Capture the current revision level for the part and drawing.
  • Reason for first article inspection identified
    Select the reason the first article inspection is being performed.
  • Manufacturing source and location recorded
    Record the manufacturing site, work center, or supplier source used to produce the part.
  • Customer purchase order or contract number recorded
    Capture the customer PO, contract, or release number associated with the first article.

AS9102 Form 2 - Product Accountability

  • Raw material certification matches drawing specification
    Verify the material certification matches the specified alloy, grade, temper, form, and applicable specification.
  • Material heat/lot number traceable to received certification
    Confirm the heat, lot, or batch number on the part traces to the certification package.
  • Special process certifications reviewed
    Select all special processes applicable to the part and verify supporting certifications are present.
  • Certificate of Conformance present for purchased or processed items
    Confirm certificates of conformance are available for all applicable purchased or outsourced items.
  • Functional test or product verification evidence reviewed
    Verify any required functional, fit, or product-level test evidence is complete and acceptable.
  • Nonconforming material or concessions identified
    Identify any open nonconformance, deviation, waiver, or concession affecting the first article.

Dimensional Verification

  • All drawing dimensions measured and recorded
    Confirm every applicable dimension, note, and characteristic on the drawing has been measured or otherwise accounted for.
  • Critical-to-quality characteristics within tolerance
    Verify all critical or key characteristics meet the specified tolerance limits.
  • Measured dimensions recorded with units
    Enter measured values and units for the inspected characteristic or attach the detailed measurement report.
  • Tolerance limits recorded
    Record the nominal dimension and tolerance limits used to evaluate the measured result.
  • Measurement method identified
    Select the primary method used to verify the characteristic.
  • Out-of-tolerance characteristics documented
    Document any characteristic that is out of tolerance and reference the associated nonconformance record.

AS9102 Form 3 - Characteristic Accountability

  • Each drawing characteristic assigned a unique characteristic number
    Confirm each requirement is uniquely numbered or otherwise cross-referenced for traceability.
  • Characteristic description matches drawing requirement
    Verify the characteristic description matches the drawing note, dimension, or specification requirement.
  • Inspection result recorded for each characteristic
    Confirm pass/fail or measured result is recorded for every characteristic.
  • Evidence of inspection method or report attached
    Attach or reference the inspection report, CMM output, or other supporting evidence.

Final Review and Approval

  • All required AS9102 forms complete
    Confirm Forms 1, 2, and 3 are complete and internally consistent.
  • Open nonconformances or corrective actions documented
    Record any open issues requiring containment, corrective action, or customer disposition.
  • Inspector signature
    Inspector signs to confirm the first article inspection was completed accurately.
  • Quality approval signature
    Quality representative approves the completed first article package.
Ask AI Template Studio

Let's customize First Article Inspection AS9102.

Tell me how you'd like to adapt it. For example:

  • Add a question about delivery time.
  • Make it shorter — 5 questions max.
  • Tailor it for the hospitality industry.
  • Translate the labels into Spanish.
Ask AI Product Advisor

Hi! I'm the MangoApps Product Advisor. I can help you with:

  • Understanding our 40+ workplace apps
  • Finding the right solution for your needs
  • Answering questions about pricing and features
  • Pointing you to free tools you can try right now

What would you like to know?