Factory Acceptance Test (FAT) Report Compilation - Switchgear

Factory Acceptance Test (FAT) Report Compilation - Switchgear

Inspection template for compiling switchgear factory acceptance test results, nameplate data, drawings, and witness records into a customer-ready FAT package for order closeout.

Test Identification and Order Details

  • Customer, project, and purchase order match the released order record
  • Switchgear lineup, section count, and voltage class match the approved submittal
  • FAT date, location, and witness status documented
  • Applicable drawing and revision list attached
  • FAT report package index completed and page numbering is sequential

Safety Preconditions and Test Readiness

  • LOTO / test isolation controls documented for energized test steps
  • Required PPE identified for the FAT area and test activities
  • Test instruments identified with current calibration status
  • Instrument calibration certificates attached or referenced
  • Test area clear, barricaded if required, and accessible only to authorized personnel

Nameplate and Assembly Data

  • Main nameplate data matches the approved bill of material and submittal
  • Manufacturer, model, serial number, and enclosure rating recorded
  • Rated voltage, current, frequency, and short-circuit rating recorded
  • Component nameplates and device tags are legible in the package photos or attachments
  • Assembly revision, wiring diagram revision, and firmware/software version documented where applicable

Routine Test Results

  • Visual and mechanical inspection completed with no unresolved deficiencies
  • Insulation resistance test results recorded
  • Contact resistance or continuity test results recorded
  • Functional operation of breakers, interlocks, and control devices verified
  • Trip, close, and indication functions operate as intended
  • Any deviations, non-conformances, or punch list items documented

Drawings, Checklists, and Closeout

  • As-built drawings, schematics, and wiring diagrams included
  • Inspection checklist and test forms are fully completed and signed
  • Customer witness signature captured when witnessing was required
  • Manufacturer quality or engineering sign-off captured
  • FAT package approved for shipment and order closeout
Ask AI Template Studio

Let's customize Factory Acceptance Test (FAT) Report Compilation - Switchgear.

Tell me how you'd like to adapt it. For example:

  • Add a question about delivery time.
  • Make it shorter — 5 questions max.
  • Tailor it for the hospitality industry.
  • Translate the labels into Spanish.
Ask AI Product Advisor

Hi! I'm the MangoApps Product Advisor. I can help you with:

  • Understanding our 40+ workplace apps
  • Finding the right solution for your needs
  • Answering questions about pricing and features
  • Pointing you to free tools you can try right now

What would you like to know?