Duct Leakage Test SMACNA Class Acceptance
Duct Leakage Test SMACNA Class Acceptance
Field inspection template for documenting duct leakage testing against SMACNA leakage class acceptance criteria, including seal class, test pressure, measured CFM leakage, and pass/fail versus design allowable.
Inspection Identification
-
Project name / job number
Record the project name and internal job or work order number.
-
System ID / duct section inspected
Identify the duct system, branch, zone, or test section covered by this record.
-
Inspection date and time
Document when the leakage test was performed.
-
Inspector name and company
Enter the qualified inspector or testing technician and company name.
Duct System and Design Criteria
-
Duct system type
Select the duct system category being tested.
-
SMACNA leakage class / seal class
Record the specified leakage class or seal class used to determine allowable leakage.
-
Design allowable leakage (CFM)
Enter the maximum allowable leakage for the test section based on the project criteria.
-
Test pressure specified by design
Record the required test pressure used to establish acceptance.
Test Setup and Preconditions
-
Test section isolated and sealed
Verify the duct section was isolated from the rest of the system and all openings were sealed for the test.
-
Test apparatus calibrated and suitable for use
Confirm the leakage test equipment was calibrated and appropriate for the pressure range being measured.
-
Ambient conditions recorded
Document relevant site conditions that could affect the test, such as temperature, wind, or access constraints.
-
Access to test points unobstructed
Verify access to test ports, joints, and sealed openings was available for inspection.
Leakage Test Results
-
Actual test pressure
Record the pressure achieved during the leakage test.
-
Measured leakage
Enter the measured leakage rate for the duct section at the test pressure.
-
Leakage within allowable limit
Confirm the measured leakage does not exceed the design allowable leakage.
-
Test result
Record the final acceptance outcome for the tested duct section.
Deficiencies, Corrective Actions, and Sign-Off
-
Deficiencies or non-conformances noted
Describe any leakage sources, sealing defects, access issues, or other non-conformances observed during the test.
-
Corrective action required
Indicate whether repair, resealing, or retesting is required before acceptance.
-
Inspector signature
Inspector attestation that the test record is accurate and complete.
-
Owner / AHJ / commissioning representative sign-off
Optional acceptance acknowledgment by the owner, AHJ, or commissioning representative.