Crane Daily Pre-Use Inspection
Crane Daily Pre-Use Inspection
Daily mobile crane pre-use inspection for hooks, ropes, load indicators, outriggers, and ground conditions.
Inspection Details
-
Crane identification recorded
Record crane make/model, unit number, and asset ID.
-
Date and shift recorded
Record the inspection date and shift start time.
-
Inspector is a competent person or authorized operator
Confirm the inspection is being completed by a qualified person familiar with the crane and site conditions.
Hooks, Wire Ropes, and Rigging Interface
-
Hook latch present and functional
Verify the safety latch is installed, closes fully, and prevents accidental disengagement.
-
Hook shows no visible deformation, cracks, or excessive wear
Inspect the hook body, throat, and shank for bending, twisting, cracks, or other damage.
-
Wire rope has no broken wires, kinks, crushing, birdcaging, or corrosion
Inspect all visible rope sections for damage, distortion, or deterioration.
-
Wire rope reeving and spooling are correct
Confirm rope is seated correctly on drums and sheaves with no cross-winding or improper reeving.
-
Sheaves, blocks, and visible fasteners are secure and free of damage
Check for missing pins, loose hardware, cracked sheaves, or abnormal wear.
Load Indicators, Controls, and Safety Devices
-
Load moment indicator or rated capacity device functions properly
Verify the load indicator, rated capacity limiter, or equivalent device powers on and displays normal status.
-
Load chart is present and legible in the cab
Confirm the correct load chart for the crane configuration is available and readable.
-
Controls, pedals, and emergency stop operate normally
Check that control response is smooth, labeled, and free from sticking or abnormal delay.
-
Anti-two-block, limit switches, and warning alarms are functional
Verify applicable audible/visual warnings and safety interlocks operate as intended.
Outriggers, Stabilizers, and Leveling
-
Outriggers and stabilizers extend and retract smoothly
Check for hydraulic leaks, binding, damaged cylinders, or uneven movement.
-
Outrigger pads and cribbing are present, sized appropriately, and in good condition
Confirm pads/cribbing are adequate for the load and free of cracks, splits, or instability.
-
Crane is level within manufacturer limits
Record the measured level or slope before operation.
-
Outrigger area is free of obstructions and overhead hazards
Verify there is adequate clearance for full deployment and operation.
Ground Conditions and Work Area
-
Ground bearing surface is firm, stable, and suitable for crane setup
Inspect for soft soil, voids, sinkage, washouts, trenches, or other conditions that could affect stability.
-
Ground is free of slope, settlement, or conditions that exceed site limits
Confirm the setup area will support the crane and load without unacceptable movement.
-
Work area is clear of personnel and nonessential equipment
Verify the lift zone is controlled and exclusion boundaries are established as needed.
-
Overhead and nearby hazards identified
Identify hazards present in the work area before lifting.
Corrective Actions and Sign-Off
-
Deficiencies documented with corrective action
Record all deficiencies, non-conformances, and actions taken before the crane is placed into service.
-
Inspection completed and signed
Inspector signature confirming the pre-use inspection was completed.