Civil Underground Utility Locate Verification
Civil Underground Utility Locate Verification
Inspection template for verifying 811 utility locate markings, white-lining, spotter controls, pre-digging checks, and excavation depth compliance before civil digging work begins.
Locate Ticket and Work Area Verification
- 811 ticket is active, valid, and available on site
- Planned dig area matches the ticket scope and marked limits
- Work area has been re-marked or refreshed if locate marks are faded or disturbed
- Utility owner responses and special instructions are reviewed before digging
- No unverified utility conflicts are present in the planned excavation path
- Pre-dig briefing completed with crew and competent person
White-Line and Surface Markings
- White-lining clearly defines the intended excavation area
- Locate markings are visible, continuous, and not obscured by debris or traffic
- Marking colors and identifiers are consistent with utility owner markings
- Tolerance zone boundaries are identified and understood by the crew
- Markings remain intact after site access, traffic control, or equipment staging
Spotter and Crew Controls
- Designated spotter is assigned where required
- Spotter maintains clear line of sight to excavation equipment and hazard area
- Crew uses a defined communication method with the operator and spotter
- Operator stops work when locate marks, spotter, or boundaries are unclear
- Crew members understand stop-work authority for utility exposure concerns
Pre-Digging and Exposure Controls
- Mechanical excavation is restricted within the tolerance zone until utilities are exposed or otherwise protected
- Hand digging or vacuum excavation is used where required for utility exposure
- Utility crossings, crossings depth, and known conflict points are identified before digging
- Spoil pile, equipment staging, and access routes do not obscure markings or create added utility risk
- Required PPE for excavation and utility exposure is available and in use
- Weather, soil, or site conditions require a pause or re-check before digging
Depth Check and Excavation Compliance
- Measured excavation depth is within approved limits for the current work stage
- Depth measurement method is documented and repeatable
- Exposed utilities are protected from damage, movement, or load transfer
- Any deviation from the locate plan is documented and escalated