Transformer Startup and Oil Sampling Record
Transformer Startup and Oil Sampling Record
Inspection template for documenting transformer startup conditions, pre- and post-energization insulating oil samples, DGA baseline readings, temperature, and load measurements.
Inspection Identification and Transformer Details
- Transformer asset ID and location recorded
- Startup date and time recorded
-
Transformer nameplate data verified
Confirm nameplate voltage, kVA/MVA rating, serial number, and cooling class match the asset record.
-
Pre-start condition noted
Document whether the unit is new, returned from maintenance, or re-energized after outage.
- Reference work order or commissioning record attached
Safety, Isolation, and Sampling Readiness
-
LOTO applied and verified before pre-energization sampling
Confirm lockout-tagout controls were applied in accordance with OSHA 1910.147 before any sampling or inspection activity.
-
Appropriate PPE worn for oil sampling and electrical work area
Verify gloves, eye protection, arc-rated PPE as required by the task hazard assessment, and any additional site-specific PPE.
-
Sampling valve and surrounding area clean and free of contamination
Inspect the valve, fittings, and sample port for dirt, moisture, leaks, or residue before collecting the sample.
-
Sampling container and labels prepared
Confirm clean, appropriate containers are available and sample labels are ready for pre- and post-energization identification.
-
Sampling method followed per site SOP
Document that the sample was drawn using the approved procedure to minimize air ingress and contamination.
Pre-Energization Oil Sample and Baseline Readings
-
Pre-energization oil sample collected
Record whether the baseline sample was taken before energization.
- Pre-energization sample time
- Pre-energization sample identification number
-
Pre-energization oil temperature
Record the oil temperature at the time of sampling.
- Pre-energization ambient temperature
-
Pre-energization DGA baseline submitted or queued
Confirm the sample is designated for dissolved gas analysis baseline testing and chain-of-custody is complete.
Post-Energization Startup Readings and Oil Sample
-
Transformer energized successfully
Confirm the transformer was energized without abnormal alarms, trips, or protective relay operation.
-
Post-energization oil sample collected
Record whether a follow-up sample was taken after energization for comparison to the baseline.
- Post-energization sample time
- Post-energization sample identification number
-
Post-energization DGA sample preserved for lab submission
Confirm the sample was sealed, labeled, and prepared for laboratory submittal without contamination or delay.
- Post-energization oil temperature
Operating Load, Observations, and Sign-Off
-
Initial load reading recorded
Record the transformer load at startup or shortly after stabilization.
-
Voltage and current readings recorded
Document initial operating voltage and current values for the energized transformer.
-
No abnormal noise, vibration, odor, or leakage observed
Verify the transformer is operating normally with no visible or audible deficiencies.
- Inspector signature
- Supervisor or authorized reviewer signature