Pressure Vessel Installation Inspection
Pressure Vessel Installation Inspection
Inspection template for verifying pressure vessel setting, orientation, nozzle positions, supports, anchor bolts, and installation readiness before startup.
Inspection Details
- Vessel tag number recorded
- Installation location recorded
- Inspection date and time recorded
- Inspector name and company recorded
- Reference drawing, datasheet, or SOP available on site
Vessel Setting and Orientation
- Vessel installed in correct horizontal or vertical orientation
- Vessel level, plumb, and aligned within project tolerance
- Elevation and foundation match approved installation drawings
- Required clearances maintained for access, maintenance, and code compliance
- Nameplate visible and legible after installation
Nozzles, Connections, and Appurtenances
- All nozzles oriented per approved drawing
- Nozzle positions and elevations match installation plan
- Flanged, threaded, or welded connections show no visible damage or misalignment
- Pressure relief device, instruments, and vents installed in correct locations
- Connections are accessible for inspection, operation, and maintenance
Supports, Anchors, and Foundation
- Supports, saddles, or skirt are installed per design
- Anchor bolts installed, tightened, and secured
- Anchor bolt condition shows no visible damage, missing hardware, or improper engagement
- Grout, baseplate, and foundation are intact with no visible cracking or voids
- Thermal expansion or movement allowances provided where required by design
Safety, Compliance, and Closeout
- Temporary shipping restraints removed or accounted for per procedure
- Lockout-tagout applied where required during inspection activities
- Inspection deficiencies documented with location and corrective action
- Photos captured for all failed critical items
- Inspector signature completed