Mobile Crane Setup and Ground Bearing Verification
Mobile Crane Setup and Ground Bearing Verification
Pre-lift inspection template for verifying mobile crane setup, outrigger pad loading, cribbing, and ground/soil bearing capacity before lifting operations begin.
Lift Setup Verification
-
Lift plan reviewed and crane configuration matches the approved setup
Verify boom length, counterweight, radius, load chart assumptions, and planned lift path match the approved lift plan.
-
Crane positioned on designated setup location
Confirm the crane is set in the intended location with adequate clearance for rotation, boom movement, and load travel.
-
Overhead hazards and power-line clearance verified
Confirm the setup location maintains required clearance from overhead power lines and other overhead obstructions.
-
Ground conditions visually assessed by competent person
Document whether the surface is level, stable, and free from voids, soft spots, fill, washout, or other instability indicators.
Ground Bearing Capacity
-
Soil or surface bearing capacity verified for expected outrigger loads
Record the assessed or engineered bearing capacity and confirm it is adequate for the maximum anticipated outrigger reaction.
-
Ground is free of voids, trenches, basements, or uncompacted backfill
Verify there are no hidden subsurface hazards that could compromise crane stability under load.
-
Surface settlement or rutting observed during setup
Check for visible sinking, cracking, heaving, or rutting after positioning and before lifting begins.
-
Drainage and moisture conditions acceptable for crane support
Confirm the area is not saturated, flooded, or undermined by runoff in a way that reduces bearing capacity.
Outriggers, Pads, and Cribbing
-
Outriggers fully extended and locked in the required position
Verify all outriggers are deployed per manufacturer instructions and secured before any lift is attempted.
-
Outrigger pads or mats sized appropriately for the load
Confirm pad or mat size is suitable for the expected outrigger reaction and ground conditions.
-
Pads centered and fully seated on stable support
Verify each pad is level, centered, and in full contact with the support surface without edge loading.
-
Cribbing is sound, level, and properly stacked
Inspect cribbing for uniform material, stable stacking pattern, and absence of cracks, splits, or shifting.
-
No improvised materials used for support
Confirm that bricks, blocks, loose fill, or other non-approved materials are not being used in place of proper mats or cribbing.
Controls, Documentation, and Sign-Off
-
Setup verified by competent person or designated inspector
Confirm the person completing the inspection is authorized and competent to evaluate crane setup and ground conditions.
-
Deficiencies documented with corrective actions assigned
Record all deficiencies, the required corrective action, and the person responsible for resolution before the lift proceeds.
-
Photos captured of crane setup and outrigger support points
Attach photos showing crane position, outrigger pads, cribbing, and any ground support measures used.
-
Inspection completed and approved for lift start
Final confirmation that the crane setup, ground bearing, and outrigger support conditions are acceptable to begin lifting operations.