Audit Setup and Tier Verification

  • Audit tier matches the scheduled rotation for this date/shift
    Verify the inspector is the assigned tier for this audit cycle and shift.
  • Audit date, time, area, and shift are recorded correctly
    Confirm the audit record identifies the correct production area, line, cell, or process and the active shift.
  • Required audit frequency has been met for this area
    Confirm the audit was completed within the required cadence for the process or area.
  • Audit evidence reviewed against the current version of the checklist
    Verify the checklist version in use matches the current approved standard.
  • Inspector name and role are documented
    Record the person completing the audit and their role or tier.
  • Audit start time
    Record the time the audit began.

Question Rotation Compliance

  • Question set used matches the required rotation for this audit cycle
    Confirm the auditor used the correct question group or rotation block for this date/shift.
  • Questions are specific, observable, and tied to standard work
    Verify the questions focus on observable process controls rather than general opinions.
  • At least one process step was observed directly during the audit
    Confirm the auditor observed the process or workstation rather than relying only on verbal confirmation.
  • Any skipped questions were justified and documented
    If a question was not applicable, confirm the reason was recorded.
  • Question rotation exceptions
    Document any deviations from the normal question rotation, including temporary process changes or special audits.
  • Questions selected covered the highest-risk process controls
    Confirm the audit included questions that address the most critical process risks for the area.

Process Observation and Standard Work

  • Observed process matches documented standard work
    Verify the actual work practice aligns with the approved standard work or SOP.
  • Visual controls are present and being used as intended
    Confirm labels, markings, boards, or other visual controls are available and effective.
  • Any non-conformance observed was documented with clear evidence
    Record the deficiency, location, and what was observed.
  • Observed process condition rating
    Rate the overall condition of the process area based on adherence to standard work and control stability.
  • Immediate containment action taken if needed
    Document any immediate action taken to contain the issue during the audit.
  • Process owner present during observation
    Confirm the area owner, lead, or operator was available for clarification when needed.

Closure Tracking and Corrective Actions

  • Open findings from prior audits are reviewed before closing the audit
    Confirm previous audit actions were checked for status and progress.
  • Each open finding has an assigned owner and due date
    Verify every open item has a responsible person and target completion date.
  • Closure evidence is attached or referenced for completed actions
    Confirm completed actions have objective evidence such as photos, records, or updated documents.
  • Corrective actions are effective and prevent recurrence
    Assess whether the implemented action addresses the root cause and is sustaining.
  • Aging open items older than the escalation threshold are identified
    Record any overdue items requiring escalation.
  • Closure tracking notes
    Add notes on status, barriers, or follow-up needed for open items.

Supervisor Escalation and Follow-Up

  • Supervisor was notified for critical or overdue findings
    Verify escalation occurred for items requiring management attention.
  • Escalation path followed matches the site procedure
    Confirm the issue was escalated to the correct supervisor, manager, or quality owner.
  • Follow-up date for escalated items is documented
    Record the planned follow-up review date for unresolved issues.
  • Escalated item summary
    Summarize the issue, owner, and current status for management review.
  • Supervisor acknowledged the escalation
    Confirm the supervisor reviewed or acknowledged the issue.
  • Inspector signature
    Signature of the person completing the layered process audit.
Ask AI Template Studio

Let's customize Layered Process Audit.

Tell me how you'd like to adapt it. For example:

  • Add a question about delivery time.
  • Make it shorter — 5 questions max.
  • Tailor it for the hospitality industry.
  • Translate the labels into Spanish.
Ask AI Product Advisor

Hi! I'm the MangoApps Product Advisor. I can help you with:

  • Understanding our 40+ workplace apps
  • Finding the right solution for your needs
  • Answering questions about pricing and features
  • Pointing you to free tools you can try right now

What would you like to know?