Press Setup Verification
- Press is isolated and lockout-tagout is cleared only after setup verification
- Die and tooling are installed, secured, and aligned to the job specification
- Press settings match the current job traveler or setup sheet
- Shut height is set to the specified value
Tonnage and Mechanical Readiness
- Required tonnage is within press capacity for the job
- Clutch, brake, and emergency stop controls function as intended
- No abnormal noise, vibration, leaks, or loose components are present
Safety Guards and Feed Line Protection
- Point-of-operation guards or safeguarding devices are in place and functional
- Feed line guards, barriers, and pinch-point protection are installed
- Light curtains, interlocks, or presence-sensing devices are clean and operational
- Guarding does not interfere with safe material feed or die clearance
Material Readiness and Feed Alignment
- Correct material type, thickness, and coil/blank specification are staged
- Material is free of visible damage, excessive burrs, rust, or contamination
- Feed alignment and entry path are set to prevent skew, jam, or misfeed
Pre-Run Sign-Off
- Area is clear of tools, loose parts, and non-essential personnel
- Operator confirms the press is ready for first-piece production
- Supervisor or authorized lead has reviewed and approved the setup