A risk might happen. A dependency must happen first.
A risk is something uncertain that could hurt delivery, so the team watches it and plans a response. A dependency is a piece of work another team has to finish before yours can start. Handle each with a named role and a next review point.
The examples are authored for the sample Northstar move and are not pulled from a risk system.
One of each, side by side
Risk: late room-layout confirmation
Departments might not confirm meeting-room needs by Week 3, which would delay the floor plan.
- Consequence: Week 4 plan approval slips
- Response: the Project Lead sends a reminder at Week 2
- Role: Department Move Coordinators
Dependency: facilities approval of the floor plan
IT cannot order switches and desk phones until Facilities approves where desks and rooms go.
- Consequence: Week 6 order cannot be placed
- Needed by: end of Week 4
- Role: Workplace Facilities Manager
Which is it?
Ask: is this certain to be needed, and does another team own it? If yes, it is a dependency. If it might occur, it is a risk. If both apply, record the dependency and add the risk that it slips.
Sample register
Illustrative entries, with no status shown. Current status sits in the project's work tracker.
| Item | If it slips | Next review | Role |
|---|---|---|---|
| Dependency: floor plan approved | Equipment order waits | Thursday check-in, Week 3 | Workplace Facilities Manager |
| Dependency: Floor 2 network tested | Phase 1 move cannot start | Week 8 check-in | IT Service Owner |
| Risk: late room-layout confirmation | Plan approval slips a week | Week 2 reminder | Project Lead |
| Risk: supplier delivery after Week 7 | Phase 1 date reconsidered | Week 6 check-in | IT Service Owner |
When something changes
-
1
Describe the change in a sentence
What is different, since when, and what you expect to happen next.
-
2
Name the affected milestone
Use the Waits for column on the Milestones page to find it.
-
3
Tell the coordinating role
Message the Project Lead, and the workstream owner if the item sits in their area.
-
4
Record it in the project system
The owner updates the work tracker. A recorded decision may then need revisiting on the Decisions page.